A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder?
In the case where a program stakeholder is concerned about the information they receive about a project, the responsibility for reviewing the communications management plan to ensure adequate information is provided to the stakeholder falls on:
D. Program manager.
The program manager is responsible for the overall coordination and management of the program, which includes ensuring that communication strategies are effectively implemented. This responsibility involves overseeing the communications management plan and making sure that it addresses the information needs of all stakeholders. While the project manager, communications manager, and program sponsor play significant roles in communication, it is the program manager who ultimately ensures that the communication plan is adequate and effectively executed across the program.
There is not role as communication manager in pgmp
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Meltone66
3 months, 1 week agohappykaur
10 months, 1 week agohanyulin
10 months, 3 weeks ago[Removed]
11 months agoCorners
3 years, 5 months agomgs552003
3 years, 7 months ago