Exam PgMP topic 1 question 422 discussion

Actual exam question from PMI's PgMP
Question #: 422
Topic #: 1
[All PgMP Questions]

An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.
What should the program manager do first to obtain program approval?

  • A. Prepare the stakeholder engagement plan for approval by the program steering committee.
  • B. Analyze the business environment to identify key stakeholders, and then perform a stakeholder analysis.
  • C. Conduct a brainstorming session with the program team to identify and analyze external stakeholders.
  • D. Create a project-level stakeholder analysis, and then perform a high-level program stakeholder analysis.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hanyulin
1 year, 1 month ago
B is the right answer.
upvoted 1 times
...
ekk1983
1 year, 2 months ago
B is the answer
upvoted 1 times
...
tsangckl
3 years, 10 months ago
I pick B. First identify and analysis stakeholder. engagement plan is no need to approve by steering committee.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.