exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 436 discussion

Actual exam question from PMI's PgMP
Question #: 436
Topic #: 1
[All PgMP Questions]

A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.
What should the program manager do next?

  • A. Modify the program schedule to accommodate the risk.
  • B. Incorporate the project risk into the program risk response strategy.
  • C. Instruct the project manager to escalate the risk to the program sponsor.
  • D. Ask the road construction project manager to manage the risk at the project level.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
1 year ago
Selected Answer: B
In this situation, where a project risk related to interdependency with another project has crossed its risk threshold, the most appropriate action for the program manager would be: B. **Incorporate the project risk into the program risk response strategy.** This step involves integrating the identified risk into the broader risk response strategy of the program. It acknowledges the interdependencies between projects within the program and ensures that the response is coordinated and effective at the program level, rather than being handled in isolation at the project level. This approach is vital for managing risks that have implications across multiple projects within a program.
upvoted 1 times
...
hanyulin
1 year, 1 month ago
Selected Answer: B
B is the right answer.
upvoted 1 times
...
hanyulin
1 year, 1 month ago
Selected Answer: C
C is the right answer.
upvoted 1 times
hanyulin
1 year, 1 month ago
I am wrong, it is b.
upvoted 1 times
...
...
ekk1983
1 year, 2 months ago
what about D ?
upvoted 1 times
...
tsangckl
3 years, 10 months ago
I pick B, Program sponsor is not directly work to resolve the program risk.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...