exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 258 discussion

Actual exam question from PMI's PgMP
Question #: 258
Topic #: 1
[All PgMP Questions]

What does CPI value less than 1.0 indicates?

  • A. Cost overrun for work completed
  • B. Scheduled performance is great
  • C. Cost underrun of performance to date
  • D. Cost for completed work is as per estimate
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SyedCert
3 years ago
CPI = EV/AC ( > 1 : Under planned cost, < 1 : Over planned cost) CV = 1 on budget/schedule (hence D)
upvoted 1 times
Salim_7
2 years, 8 months ago
CPI is "LESS" than 1.0 => Cost overrun hence A
upvoted 3 times
...
...
tsangckl
3 years, 8 months ago
yes, less then. A
upvoted 3 times
...
snow5
3 years, 9 months ago
less than 1 means overrun, D if equal 1
upvoted 1 times
...
tsangckl
3 years, 10 months ago
it is D for sure.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...