A. Cost overrun for work completed.
The CPI is a measure used in project management to assess the cost efficiency and financial effectiveness of a project. It is calculated by dividing the Earned Value (EV) of the work performed by the Actual Cost (AC) of the work. A CPI value of less than 1.0 means that the project is costing more than planned for the work that has been completed, indicating a cost overrun. Essentially, for every unit of currency spent, less value is being earned than was anticipated in the project plan.
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
[Removed]
10 months, 3 weeks agoSyedCert
2 years, 10 months agoSalim_7
2 years, 5 months agotsangckl
3 years, 5 months agosnow5
3 years, 6 months agotsangckl
3 years, 7 months ago