exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 316 discussion

Actual exam question from PMI's PgMP
Question #: 316
Topic #: 1
[All PgMP Questions]

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.
Based on this information, the program manager determines which of the following?

  • A. The schedule is US$30,000 under budget
  • B. The cost is US$20,000 under budget
  • C. The schedule is US$10,000 over budget
  • D. The cost is US$20,000 over budget
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NordSee
3 weeks ago
Selected Answer: A
This is some kind of tricky question but I've learned same calculation formula with "NawrasHamwi". The correct answer shall be Option-A.
upvoted 1 times
...
Musfiq
9 months, 1 week ago
Selected Answer: C
With the rationale that actual cost is $10K more than the EV though this is not standard definition.
upvoted 1 times
...
hanyulin
1 year, 1 month ago
Selected Answer: C
No correct answer! But chose C.
upvoted 2 times
Musfiq
9 months, 1 week ago
Agree. Based on the information SV or CPI could be calculated which are $20000 and 0.97 respectively.
upvoted 1 times
...
...
NawrasHamwi
2 years, 1 month ago
Correct answer is A: PV = 320K, AC = 350K , EV = 340K SV = EV-PV = 20K, CV = EV-AC = -10K SV =20 and CV =-10, So the overall variance is SV - CV =10 ahead of schedule. Presently you are in the third month so in 3 months the situation is 10k ahead of schedule. The completion period is 9 months. If in 3 months you are 10k ahead of schedule so in 9 months will be 30k ahead of schedule.
upvoted 3 times
...
NawrasHamwi
2 years, 1 month ago
Selected Answer: A
Correct answer is C: PV = 320K, AC = 350K , EV = 340K SV = EV-PV = 20K, CV = EV-AC = -10K SV =20 and CV =-10, So the overall variance is SV - CV =10 ahead of schedule. Presently you are in the third month so in 3 months the situation is 10k ahead of schedule. The completion period is 9 months. If in 3 months you are 10k ahead of schedule so in 9 months will be 30k ahead of schedule.
upvoted 2 times
...
Hazem1976
3 years ago
Correct Answer is C: EAC = 2,110,000 BAC = 2,100,000 VAC = 2,100,000 - 2,110,000 = -10,000 (Negative variance indicates Over Budget)
upvoted 1 times
...
Corners
3 years, 9 months ago
There is no correct answer! The project is 20k ahead of schedule and 10k over budget.
upvoted 1 times
...
tsangckl
3 years, 10 months ago
cost ... on D
upvoted 1 times
...
tsangckl
3 years, 10 months ago
D answer should.$10000 overbudget
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...