Actual exam question from PMI's PgMP
Question #: 406
Topic #: 1
[All PgMP Questions]

A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.
What should the program manager do first?

  • A. Develop the benefits sustainment plan.
  • B. Develop the program management plan.
  • C. Develop the program roadmap.
  • D. Develop the component project schedules.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
4 months ago
Selected Answer: C
C. Develop the program roadmap. The program roadmap is a strategic tool that outlines the major milestones and benefits throughout the lifecycle of the program. By developing a program roadmap, the program manager can identify when and how incremental benefits can be realized in alignment with the organization's expectations. The roadmap provides a high-level timeline that helps to visualize the delivery of benefits and can inform more detailed planning, including the program management plan and component project schedules. It is a foundational document that guides the subsequent planning and execution phases of the program.
upvoted 1 times
...
hanyulin
4 months ago
Selected Answer: C
C is the right answer
upvoted 1 times
...
Corners
2 years, 11 months ago
+1. The correct answer is C. Sustainment plan does not show incremental delivery of benefits.
upvoted 1 times
...
tsangckl
3 years ago
It is C , roadmap not A
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...