Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
Location Chicago IL, USA

Exam PgMP topic 1 question 407 discussion

Actual exam question from PMI's PgMP
Question #: 407
Topic #: 1
[All PgMP Questions]

A component is scheduled to close at the end of the week.
What should the program manager verify prior to allowing the component to close?

  • A. The component has released resources to meet program objectives
  • B. The component has met the quality requirements to meet program objectives
  • C. The component has met the schedule requirements to meet program objectives
  • D. The component has met the benefits realization criteria to meet program objectives
Show Suggested Answer Hide Answer

Suggested Answer: B

Comments

tsangckl
1 month, 1 week ago
It is D, verify benefits instead of quality
upvoted 1 times
...

SaveCancel