D. The component has met the benefits realization criteria to meet program objectives.
Before the closure or transition of program components, it is essential to review that the benefits were delivered according to the criteria documented in the governance plan. This includes ensuring that the component's deliverables have been produced, successful delivery has been coordinated, and any transition activities necessary for ongoing benefits have been established. It is crucial that these steps are taken to confirm the component's alignment with the overall program objectives and its contribution to the expected benefits before formal program closure is authorized.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
[Removed]
4 months agohanyulin
4 months, 1 week agoCorners
2 years, 11 months agotsangckl
3 years ago