Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PgMP topic 1 question 437 discussion

Actual exam question from PMI's PgMP
Question #: 437
Topic #: 1
[All PgMP Questions]

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.
What should the program manager do to ensure benefits realization?

  • A. Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay.
  • B. Inform the program sponsor and the steering committee of the delay, and validate the program business case.
  • C. Analyze the impact of the delay, review risks identify any corrective actions, and update the benefits management plan.
  • D. Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
happykaur
3 months, 1 week ago
In this scenario, to ensure benefits realization after learning about the delay in progress, the program manager should: C. **Analyze the impact of the delay, review risks, identify any corrective actions, and update the benefits management plan.** This option involves a comprehensive approach to address the delay. It starts with understanding the impact of the delay on the overall program, reviewing how this impacts the risk profile, and then identifying appropriate corrective actions. Updating the benefits management plan is crucial to align it with the new realities of the program, ensuring that the program's benefits are still achievable despite the delay.
upvoted 1 times
...
hanyulin
4 months, 1 week ago
Selected Answer: C
I pick C
upvoted 1 times
...
ekk1983
5 months, 2 weeks ago
it should be C
upvoted 1 times
...
yinfei
2 years, 1 month ago
but why update the benefits management plan? is it update the prgram schedule ?
upvoted 1 times
...
tsangckl
3 years ago
I pick C, not understand why pmo can help on shipyard work
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...