Actual exam question from PMI's PgMP
Question #: 281
Topic #: 1
[All PgMP Questions]

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

  • A. Program management performance variances, business criteria reweighting, root cause identification, and statistical sampling.
  • B. Interviewing, SWOT analysis, run chart, and matrix-based charts.
  • C. Earned value management, financial reporting systems, performance measurement techniques, and program management information systems.
  • D. Delphi technique, scatter diagram, Pareto chart, and organization charts.
Show Suggested Answer Hide Answer

Suggested Answer: A

Comments

tsangckl
1 month, 1 week ago
My answer is C