Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PgMP topic 1 question 41 discussion

Actual exam question from PMI's PgMP
Question #: 41
Topic #: 1
[All PgMP Questions]

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

  • A. Finish on constraints
  • B. Discretionary dependencies
  • C. Mandatory dependencies
  • D. Benefits management dependencies
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
4 months, 2 weeks ago
Selected Answer: B
B. Discretionary dependencies Explanation: Finish-on constraints: These are constraints that dictate when a particular activity must finish. Mandatory dependencies: These are dependencies that are inherent and required by the nature of the work being performed. The activities must be done in a particular order. Benefits management dependencies: This term is not a standard concept related to the sequencing of activities. Discretionary dependencies: Also known as preferential logic or soft logic, these are dependencies that are defined by the project team based on their judgment or preferences. Activities with discretionary dependencies can be rearranged to optimize the schedule, alleviate conflicts, or manage risks, as mentioned in your scenario.
upvoted 1 times
...
encqizo
1 year, 12 months ago
Definitely B
upvoted 1 times
...
SyedCert
2 years, 3 months ago
I agree, it's B
upvoted 2 times
...
Karamurat
2 years, 6 months ago
"A mandatory dependency is one that “must be” carried out at a particular time." https://www.project-management-prepcast.com/free/pmp-exam/tips/316-the-difference-between-mandatory-and-discretionary-project-management-dependencies-revealed
upvoted 3 times
...
tsangckl
3 years ago
in any order. it is B.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...