Exam PMI-ACP topic 1 question 530 discussion

Actual exam question from PMI's PMI-ACP
Question #: 530
Topic #: 1
[All PMI-ACP Questions]

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.
What should the agile practitioner do?

  • A. Jointly meet with the team and product owner to discuss options and determine the end date
  • B. Announce that the team has exceeded the predicted velocity, and that the end date will be earlier than planned
  • C. Ask the product owner to include additional features in the product backlog, then replan subsequent iterations
  • D. Ask the team to decrease velocity to meet contractual obligations and document this decision
Show Suggested Answer Hide Answer

Suggested Answer: A

Comments

Rawanh
1 month, 1 week ago
I'm not sure if the correct answer is A, as the sprint due date cannot be changed.
upvoted 1 times
...