Actual exam question from PMI's PgMP
Question #: 426
Topic #: 1
[All PgMP Questions]

A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

  • A. Deploy a team to develop the program management plan.
  • B. Develop estimates for scope, resources, and cost.
  • C. Identify the program management components, and develop the resource management plan.
  • D. Review and update the benefits management plan and link it to program outcomes.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
1 year ago
Selected Answer: A
Once the program charter for automating a new-client onboarding process is formally accepted, the next step should be: A. Deploy a team to develop the program management plan. The program management plan is a crucial document that outlines how the program will be executed, monitored, and controlled. It includes plans for managing scope, schedule, cost, quality, resources, communication, risks, procurement, and stakeholders. Developing this plan right after the charter is accepted is essential to guide all subsequent activities in the program. This plan sets the foundation for how the program will be managed and ensures that all aspects of the program are considered and planned for effectively.
upvoted 1 times
...
happykaur
1 year ago
Selected Answer: A
Once the program charter for automating a new-client onboarding process is formally accepted, the next step should be: A. Deploy a team to develop the program management plan. The program management plan is a crucial document that outlines how the program will be executed, monitored, and controlled. It includes plans for managing scope, schedule, cost, quality, resources, communication, risks, procurement, and stakeholders. Developing this plan right after the charter is accepted is essential to guide all subsequent activities in the program. This plan sets the foundation for how the program will be managed and ensures that all aspects of the program are considered and planned for effectively.
upvoted 1 times
...
hanyulin
1 year, 1 month ago
Selected Answer: A
I vote A
upvoted 1 times
...
ekk1983
1 year, 2 months ago
I vote for A
upvoted 1 times
...
Corners
3 years, 8 months ago
A is the right answer.
upvoted 1 times
...
tsangckl
3 years, 9 months ago
Develop estimates for scope, resources, and cost. is do before the program charter. Then go into program planing phase. So Answer is A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...