exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 51 discussion

Actual exam question from PMI's PgMP
Question #: 51
Topic #: 1
[All PgMP Questions]

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

  • A. Lead time
  • B. Crashing
  • C. Lag time
  • D. Fast tracking
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Salim_7
6 months, 3 weeks ago
Correct answer is B. Fast tracking increases risks
upvoted 1 times
...
6sense
2 years, 2 months ago
Resource adding is always Crashing
upvoted 4 times
...
snow5
2 years, 7 months ago
correct is Fast track
upvoted 2 times
UHS
10 months, 2 weeks ago
its crashing when resources are added. Fast track is when tasks that can be done in parallel are identified to compress the schedule
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...