Exam PgMP topic 1 question 355 discussion

Actual exam question from PMI's PgMP
Question #: 355
Topic #: 1
[All PgMP Questions]

A sponsor decides that the business environment is unfavorable for continuation of a program. The sponsor asks that the program be closed.
What items should be completed as part of the program's final report?

  • A. Lessons learned, successes and failures, and financial and performance assessments
  • B. Final updates to the benefits register, successes and failures, and resource disposition
  • C. Financial and performance assessments, successes and failures, and reason(s) for program closure
  • D. Knowledge transition, successes and failures, and reason(s) for program closure
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
My opinion, A is correct. I don't see term or standard "reason(s) for program closure. I think that reason(s) for program closure is in lessons learned.
upvoted 1 times
...
happykaur
1 year, 4 months ago
Selected Answer: A
As part of the final report for a program that is being closed by the sponsor due to an unfavorable business environment, the items that should be included are: A. **Lessons learned, successes and failures, and financial and performance assessments.** This option covers a comprehensive closure report. Lessons learned provide valuable insights for future initiatives. Documenting successes and failures offers a clear view of what worked and what didn't. Financial and performance assessments provide a final overview of how the program fared against its objectives and budget.
upvoted 1 times
happykaur
1 year, 3 months ago
C can also be considered
upvoted 1 times
...
...
hanyulin
1 year, 5 months ago
Selected Answer: C
C is the right answer.
upvoted 1 times
...
tsangckl
4 years ago
This is a tricky questions. A and C is also correct for program finial report. A and C is also correct. But if you ask me to pick one. I pick C. As it is a program termination. Reason(s) for program closure needs to be record in the report.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...