Question #: 347
Topic #: 1
[All PgMP Questions]

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared.
During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

  • A. Attitude about the program, external political position, and technical expertise
  • B. Level of influence and participation and attitude about the program
  • C. Expectations of program benefits, level of influence, and organizational culture
  • D. Level of support/opposition, technical expertise, and organizational culture
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
C is the best answer
upvoted 1 times
tungdt
10 months, 2 weeks ago
Sorry, I think again. I choose B. Expectations of program benefits for Business Case, program charter (high level). The question asks "stakeholders aspects" so organizational culture don't make sense and organizational culture for change.
upvoted 1 times
...
...
happykaur
1 year, 2 months ago
Selected Answer: C
Spm 5.3
upvoted 1 times
...
happykaur
1 year, 4 months ago
Selected Answer: C
During stakeholder engagement planning for a program, the program manager should consider the following aspects of stakeholders: C. Expectations of program benefits, level of influence, and organizational culture. Understanding stakeholders' expectations of program benefits is crucial for aligning the program's objectives with their needs and interests. The level of influence of each stakeholder can determine the impact they have on the program's success. Additionally, considering the organizational culture is important for effective communication and engagement strategies. This combination helps in devising a stakeholder engagement plan that is responsive to the needs and dynamics of all involved parties.
upvoted 1 times
...
hanyulin
1 year, 5 months ago
Selected Answer: C
C is the right answer
upvoted 2 times
...
[Removed]
1 year, 5 months ago
C. Expectations of program benefits, level of influence, and organizational culture. These aspects are crucial for effective stakeholder engagement: Expectations of Program Benefits: Understanding what different stakeholders expect to gain from the program helps tailor engagement strategies to address their interests and concerns, ensuring that their needs are aligned with the program's objectives. Level of Influence: Recognizing which stakeholders have significant influence over the program or within the organization aids in prioritizing engagement efforts and managing potential impacts on the program. Organizational Culture: Being aware of the organizational culture helps in shaping the communication and engagement approaches in a way that resonates with stakeholders and aligns with the organization's values and norms.
upvoted 1 times
...
yinfei
3 years, 1 month ago
yes its C, the tricky one is B is so similar to C
upvoted 1 times
...
tsangckl
4 years ago
Answer is C ref. SPM 5.3
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...