A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million. Since the shutdown was not anticipated, what should the program manager do first?
A.
Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
B.
Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
C.
Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.
D.
Collaborate with the sponsor to determine options and negotiate a new date for the milestone.
C is not sure as impact is clear. It is an issue, not risk anymore. The answer is D.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
snow5
3 years, 5 months agotsangckl
3 years, 8 months ago