exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 300 discussion

Actual exam question from PMI's PgMP
Question #: 300
Topic #: 1
[All PgMP Questions]

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.
Since the shutdown was not anticipated, what should the program manager do first?

  • A. Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
  • B. Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
  • C. Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.
  • D. Collaborate with the sponsor to determine options and negotiate a new date for the milestone.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
3 years, 5 months ago
C is the right answer, the situation is critical and needs the prog gov to get involved.
upvoted 1 times
...
tsangckl
3 years, 8 months ago
C is not sure as impact is clear. It is an issue, not risk anymore. The answer is D.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...