An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.
In what phase is the risk management plan created?

  • A. Program definition
  • B. Program execution management
  • C. Program delivery
  • D. Program risk management planning
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
10 months, 2 weeks ago
A is correct During the program definition phase, the overall framework and foundational plans for the program are established, including the risk management plan. This phase involves identifying, assessing, and planning for potential risks that could impact the program. Creating the risk management plan early in the program ensures that risks are proactively managed throughout the program's lifecycle.
upvoted 1 times
...
[Removed]
1 year, 5 months ago
Selected Answer: A
A. Program definition phase. In the program definition phase, the program's overall approach is established, including the development of plans that will guide the program through its life cycle. This includes identifying risks and creating a risk management plan that outlines how risks will be managed throughout the program. The risk management plan is essential for identifying potential risks early on and developing strategies to mitigate them, ensuring that the program remains on track to meet its critical objectives.
upvoted 1 times
...
hanyulin
1 year, 5 months ago
Selected Answer: A
A is right.
upvoted 2 times
...
Jayoohhay
1 year, 6 months ago
Program Definition phase comprises of two sub phases - Program formulation where Business case, Charter, Roadmap and scope statement are created. The second subphase is Program Planning where required planning and documentations are completed. Correct Answer is A
upvoted 1 times
...
ekk1983
1 year, 6 months ago
A I think
upvoted 1 times
...
Corners
4 years ago
A. Risk management planning is the part of program planning subphase, it is the definition phase.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...