exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 408 discussion

Actual exam question from PMI's PgMP
Question #: 408
Topic #: 1
[All PgMP Questions]

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?

  • A. Allow the component project manager to delegate risk management responsibilities.
  • B. Assign the resolution of project-level risks to the component project manager.
  • C. Include risk escalation policies and procedures in the risk response plan.
  • D. Increase flexibility with risks that require a risk response.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
10 months, 1 week ago
Selected Answer: B
Will go with B
upvoted 1 times
...
hanyulin
10 months, 1 week ago
Selected Answer: C
C is the right answer.
upvoted 1 times
...
ekk1983
11 months, 3 weeks ago
I picked B
upvoted 1 times
...
Corners
3 years, 5 months ago
I picked B. It is not the project manager, who falls behind and delays risk plans approvals, it is a program manager who falls behind and has to delegate project level risk management actions to a project manager.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago