exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 127 discussion

Actual exam question from PMI's PMI-ACP
Question #: 127
Topic #: 1
[All PMI-ACP Questions]

A product's scope and acceptance criteria have been detailed, and the product is planned for release at the end of the next quarter.
What should the project team do next?

  • A. Estimate the project team's capacity
  • B. Determine how much work can be delivered
  • C. Calculate how much work will fit into the next iteration
  • D. Estimate items in the product backlog
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thuha1704
Highly Voted 1 year, 8 months ago
Steps to Planning a Release 1. Determine condition of satisfaction 2. Estimate user stories 3. select an iteration length 4. estimate velocity 5. Proritize US 6. select stories and release date D is correct
upvoted 5 times
...
Petrevski
Most Recent 6 months, 3 weeks ago
Selected Answer: D
D = correct
upvoted 1 times
...
Minhha3
7 months, 2 weeks ago
Vote D
upvoted 1 times
...
InvisibleBeing
9 months, 4 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
Eli8
1 year, 3 months ago
Defined AC is made in Iteration, therefore the next step is to estimate tasks=estimate capacity. Delete (D) for next step is Not to estimate stories/items from the Product Backlog, Delete (B)(C) for selected Stories for Iteration (scope) comes before defined AC, and "how much work" means the scope needs to be defined again, which is wrong. I go for (A)
upvoted 1 times
...
richck102
1 year, 4 months ago
i vote D
upvoted 1 times
...
Admirable
2 years, 2 months ago
Best Answer D. Mike Griffith pg. 323. In the release planning meeting we decompose our stories as needed for that level of planning. However, those breakdowns are still fairly coarse-grained, and meant to be preliminary. The ultimate details of the stories—the tasks—are broken down at the “last responsible moment” during iteration planning. » Estimate the tasks. After the planning meeting, we can estimate the effort required to complete each of the tasks in real time, since our estimates so far have been in story points. Estimating the tasks in real time is an optional step, but it does help confirm that our plan for the iteration is really workable.
upvoted 2 times
...
Admirable
2 years, 2 months ago
Iteration Planning according to Mike Griffith pg. 323 1. Discuss the user stories in the backlog and any dependencies 2. Select the user stories for the iteration 3. Define acceptance criteria and write acceptance tests for the stories 4. Break the stories into tasks 5. Estimate the tasks in ideal time, then assign and schedule them in real time
upvoted 1 times
...
Ceno239
2 years, 4 months ago
Should be D
upvoted 1 times
...
STW
2 years, 5 months ago
Why not D? Items are already in the backlog as scope a acceptance criteria have been defined.
upvoted 2 times
Azurance
2 years, 4 months ago
Yep, I'll go with D. without estimating backlog, one can't estimate teams capacity.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...