A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
DipakKumar
Highly Voted 3 years agoEli8
2 years, 8 months agoInvisibleBeing
2 years, 2 months agoEli8
2 years, 8 months agoWaltharius
8 months, 3 weeks agoAmatullahSulaiman
Most Recent 7 months agonewbie_pm
9 months, 3 weeks agonewbie_pm
9 months, 3 weeks agoNervys
1 year, 4 months agoImrangoshi
1 year, 7 months agowail84n
1 year, 7 months agoSiwana
1 year, 10 months agoAgile_Dario_Conde
1 year, 11 months agocutri89
2 years, 1 month agoPetrevski
2 years, 1 month agoTompaL111
2 years, 2 months agoInvisibleBeing
2 years, 3 months agoEli8
2 years, 8 months agoEli8
2 years, 8 months agoEli8
2 years, 8 months agorichck102
2 years, 9 months agoadelshenouda
3 years, 8 months ago