A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
DipakKumar
Highly Voted 3 years, 1 month agoEli8
2 years, 10 months agoInvisibleBeing
2 years, 4 months agoEli8
2 years, 10 months agoWaltharius
10 months, 1 week agoAmatullahSulaiman
Most Recent 8 months, 3 weeks agonewbie_pm
11 months, 2 weeks agonewbie_pm
11 months, 2 weeks agoNervys
1 year, 5 months agoImrangoshi
1 year, 9 months agowail84n
1 year, 9 months agoSiwana
2 years agoAgile_Dario_Conde
2 years agocutri89
2 years, 2 months agoPetrevski
2 years, 2 months agoTompaL111
2 years, 3 months agoInvisibleBeing
2 years, 4 months agoEli8
2 years, 10 months agoEli8
2 years, 10 months agoEli8
2 years, 10 months agorichck102
2 years, 11 months agoadelshenouda
3 years, 10 months ago