exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 310 discussion

Actual exam question from PMI's PgMP
Question #: 310
Topic #: 1
[All PgMP Questions]

In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

  • A. Program benefits and all component project activities
  • B. Component resources and their activity assignment/responsibility metrics
  • C. Program-level activities and integrated component projects
  • D. Program activities, component activities, and all other work
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Musfiq
5 months, 3 weeks ago
Selected Answer: C
Program Integrated Master Schedule shouldn't contain activities from component projects rather they should be taken care of by the projects' schedules themselves.
upvoted 2 times
...
happykaur
9 months, 3 weeks ago
Selected Answer: D
The program master schedule is the top-level program planning document that defines the individual component schedules and dependencies among program components (individual components and program-level activities) required to achieve the program goals. It should include those component milestones that represent an output to the program or share interdependency with other components. The program master schedule should also include activities that are unique to the program including, but not limited to, activities related to stakeholder engagement, program-level risk mitigation, and program-level reviews. The program master schedule determines the timing of individual components, enables the program manager to determine when benefits will be delivered by the program, and identifies external dependencies of the program.
upvoted 1 times
Musfiq
5 months, 3 weeks ago
Based on the explanation you provided specially milestones of components shouldn't be the right answer as C?
upvoted 1 times
...
...
[Removed]
10 months, 2 weeks ago
Selected Answer: D
Check 8.1.2.11 (Standard)
upvoted 1 times
...
snow5
3 years, 2 months ago
C is the right answer, the master determines the integration and interdependency among components
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago