Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined.
Where should you record all change requests and their status?

  • A. Change register
  • B. Integrated change control
  • C. Program Management Information System
  • D. Change log
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
6sense
3 years, 5 months ago
it must be Change log , there is no term of change register in SPM
upvoted 4 times
chaoman
3 years, 1 month ago
I concur. It should be change log indeed.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...