Question #: 209
Topic #: 1
[All PgMP Questions]

You are working with Sam, a project manager on one of the projects within your program. Sam doesn't understand all of the rules and procedures that he's required to do as a project manager in your program. What are the rules and procedures called in project that Sam must abide by?

  • A. Project governance
  • B. Process procedures
  • C. Enterprise environmental factors
  • D. Program governance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Salim_7
2 years, 9 months ago
Enterprise Environment Factors (EEFs) include all policies, practices, procedures, and legislation that exist both inside and outside of the organization that will impact the way you manage a project.
upvoted 1 times
c9619c8
3 weeks, 1 day ago
You mean OPAs, not EEFs!
upvoted 1 times
...
...
6sense
3 years, 5 months ago
must be Project Governance ; Enterprise environmental factors - does not have rules & regulation a
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.