You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?
From PMI's book "The Standard for Program Management", section 3.5.5 Scope Definition:
"The program scope statement becomes the basis for future program decisions and articulates the scope boundaries of the program"
B is correct answer
The document that should serve as the baseline for all future program decisions in the program planning processes is the Program Management Plan. This comprehensive document provides a detailed roadmap for how the program will be managed and includes key information that guides decision-making.
B. Program Management Plan.
B. Program Management Plan: This is the correct choice. The Program Management Plan is a formal, approved document used to guide both program execution and program control. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. As such, it serves as the baseline for how decisions are made throughout the program, encompassing scope, time, cost, quality, human resource, communications, risk, procurement, and stakeholder management.
B should be the right answer.
From PMI book, it clearly states that the program management plan is therefore a reference document and should be seen as a managed baseline (page 110)
From PMI's book "The Standard for Program Management", section 3.5.5 Scope Definition:
"The program scope statement becomes the basis for future program decisions and articulates the scope boundaries of the program"
"The program management plan is a single, formal, dynamic document that outlines how the program is to be managed, executed, and controlled."..."This document should ensure there are no surprises through execution on how the program is managed or decisions are made."
https://uwaterloo.ca/ist-project-management-office/methodologies/program-management/program-benefit-delivery/program-management-plan
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
trantridue
9 months, 1 week agotungdt
10 months ago[Removed]
1 year, 4 months agoencqizo
3 years agoSyedCert
3 years, 4 months agoKaramurat
3 years, 6 months agoKaramurat
3 years, 6 months ago