You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

  • A. $2,656,500
  • B. There is not enough information to know.
  • C. $3,795,000
  • D. $1,035,000
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SyedCert
10 months, 2 weeks ago
Here you go. EAC = AC + (BAC – EV) AC = $3,450,000 * 0.4 = 1,380,000 (40% is used question say spent 10% more than actual 30%) BAC = $3,450,000 (BAC - Budget at completion is provided in the question) EV = BAC * % completed i.e. 30% = $3,450,000 * 0.3 = 1,035,000 So EAC = 1,380,000 + ($3,450,000 - 1,035,000) = 3,795,000
upvoted 2 times
...
ss44
1 year, 1 month ago
please provide the calculation to arrive at the answer. thank you.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...