Question #: 11
Topic #: 1
[All PMI-ACP Questions]

A new team member asks what changes could accelerate a change to the project plan.
What should be the proper response?

  • A. Competitors joined forces with the team
  • B. The customer changed requirements
  • C. Project team members obtained additional certifications
  • D. Technology which did not interfere with the final product
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
josephsafiran
6 months, 3 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
KenjiLeeVN
1 year, 5 months ago
Selected Answer: B
B is correct
upvoted 1 times
...
Imrangoshi
1 year, 8 months ago
Selected Answer: B
B is the Correct Answer
upvoted 1 times
...
cutri89
2 years, 1 month ago
Selected Answer: B
b is right
upvoted 1 times
...
Petrevski
2 years, 1 month ago
Selected Answer: B
B - correct
upvoted 1 times
...
InvisibleBeing
2 years, 3 months ago
Selected Answer: B
B it is.
upvoted 1 times
...
7029
2 years, 4 months ago
Selected Answer: B
B is the most as changes from users are faster.
upvoted 1 times
...
gogiap
2 years, 7 months ago
B because any changes to the requirements can lead to iteration plan, release plan and ultimately project plan changes
upvoted 1 times
...
RKarpe
3 years, 6 months ago
why B?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...