Actual exam question from PMI's PMI-RMP
Question #: 85
Topic #: 1
[All PMI-RMP Questions]

A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?

  • A. Implement a workaround.
  • B. Create a change request.
  • C. Implement a contingency or fallback plan.
  • D. Review the project management plan.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
attarinho
3 months, 1 week ago
Selected Answer: C
Wrong! Workaround if the risk has not been identified nor registered in the risk register. Hence, this is active acceptance strategy where the risk is identified and for some reason no action be taken.
upvoted 1 times
...
OMG4567
7 months, 3 weeks ago
Selected Answer: A
Changed my mind… if a risk occurs, which was not identified or passive accepted, it requires a workaround. Sorry for the confusion.
upvoted 1 times
...
OMG4567
7 months, 3 weeks ago
Selected Answer: C
As the risk did not happen there is no need for a workaround. Project manager should implement a contingency or fallback plan.
upvoted 1 times
...
ahmedSayis
2 years, 5 months ago
A. Implement a workaround.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago