exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 16 discussion

Actual exam question from PMI's PMI-RMP
Question #: 16
Topic #: 1
[All PMI-RMP Questions]

What steps would be used during the qualitative risk analysis process to provide input to the risk register?

  • A. Select risks characteristics, collect and analyze data, prioritize risks, categorize risks causes, document results
  • B. Interviews, expert opinions, sponsor inputs, risk manager review, prioritize risks, and document results
  • C. Interviews, expert opinions, risk manager review, prioritize risks, and document results
  • D. Select risks characteristics, collect and analyze data, prioritize risks, discuss action plans for major risks, document results
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheAWSGuru
10 months, 4 weeks ago
A is the answer
upvoted 1 times
...
MikeMarlo
1 year ago
Selected Answer: A
- You have already done Risk Identification, so you know some details about Project Risks and you have it documented in its output: the Risk Register. The first thing, that you should start with, is Selecting risks characteristics. - Risk categorisation is also a tool of Qualitative Analysis. - Prioritize Risks is the main output of Qualitative Analysis. - Categorize Risks Analysis is also in its ITTOs. - Document results is obvious.
upvoted 1 times
...
Linkedin_Dario_Conde
1 year, 6 months ago
Selected Answer: C
C. Is correct because select risk characterictics is wrong
upvoted 1 times
...
AhmedRashad
1 year, 7 months ago
A is the correct answer
upvoted 1 times
...
Rehman7510
1 year, 9 months ago
Selected Answer: A
Select risks characteristic, collect and analyze data, prioritize risks, categorize risks causes, document results
upvoted 1 times
...
Beham
1 year, 9 months ago
Selected Answer: A
A. Select risks characteristic, collect and analyze data, prioritize risks, categorize risks causes, document results
upvoted 1 times
...
RoyalWarrior
2 years, 2 months ago
Answer C is correct. As risk categories are first selected in the Plan Risk Management Process with the help of the Risk Breakdown structure. Categories of risk are specific elements within a project or its operational environment that could go wrong during the planning, implementation, or follow-up phases of an activity. These risk categories consider things such as costs, timeline, available staff, public reception, and available inventory. They look at the details that go into making a successful project and consider what would happen if one or more of those details veered off course.
upvoted 2 times
...
aws_guru1
2 years, 2 months ago
A is correct
upvoted 1 times
...
ahmedSayis
3 years, 6 months ago
A. Select risks characteristic, collect and analyze data, prioritize risks, categorize risks causes, document results
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...