Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent.
Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk-adverse with this project.
Which of the following methods should Ben avoid to recoup the project time?