A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
NA1234567
Highly Voted 2 months, 3 weeks agofragar65
Most Recent 1 week, 3 days agopop71
2 weeks, 5 days agoLotToLearn
2 weeks, 6 days agoAditech
3 weeks, 3 days agoPragati06
3 weeks, 4 days agoAfricanTea
2 months, 3 weeks agoBry29
4 months agoJiyoung0301
5 months ago4f6ae44
6 months agoBuviD
9 months, 1 week agokhloreeen
10 months, 1 week agoRavi4french
1 year agoBakM
1 year agoNAL76
1 year agoMahi_02021988
1 year, 2 months agoEmmyomy
1 year, 2 months ago