A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
4f6ae44
2 weeks, 4 days agoAditech
3 weeks, 2 days agoBuviD
4 months agokhloreeen
4 months, 3 weeks agoRavi4french
7 months agoBakM
7 months agoNAL76
7 months, 2 weeks agoMahi_02021988
9 months agoEmmyomy
9 months, 1 week agoMbolatiana
9 months, 3 weeks agoFela80
10 months, 3 weeks agosultanalsanie
12 months agovictory108
12 months agoMakinskim
12 months agoWhydotty
1 year agoBenPappoe
1 year agoziyaetuk
1 year ago