A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
AP2023S
Highly Voted 11 months, 3 weeks agoOxyMedix
Most Recent 1 week, 6 days agosegatarasov
2 months, 1 week agoWinnersys
3 months agoDavard
3 months, 3 weeks agoMashikoane
3 months, 4 weeks agoBruce_Liu
4 months, 2 weeks agoTracyyy123
6 months, 3 weeks agoNemona1979
7 months, 1 week agosambeth
7 months, 3 weeks agoRemmy12
8 months, 1 week agoKeldon_Phan
8 months, 2 weeks agoAsakthi
9 months agobug_bloke
9 months, 1 week agosmartrammy
10 months agoAbbasTaki
11 months, 2 weeks agovictory108
11 months, 3 weeks ago