During a documentation audit of an international company, it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated.
How should the project manager have handled documentation for the project?
d482858
2 weeks, 3 days agoKennyMuffins
2 months, 2 weeks agoBruce_Liu
3 months, 1 week agojosephsafiran
3 months, 3 weeks agoUncle_Lucifer
6 months, 2 weeks agoOnly12go
6 months, 2 weeks agoadingmaki
6 months, 3 weeks agoDavid983
6 months, 3 weeks agoDavid983
6 months, 3 weeks ago1234abcdefgh
7 months, 2 weeks agovictory108
8 months, 1 week agoAish_
8 months, 3 weeks agoJamrock
8 months, 3 weeks agoSteAle
9 months, 4 weeks agoNeil20
10 months, 2 weeks agorknowles
10 months, 2 weeks agoAlekhyaT
11 months agoardas91
11 months, 1 week ago