Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 492 discussion

Actual exam question from PMI's PMP
Question #: 492
Topic #: 1
[All PMP Questions]

During project execution, the project manager discovered that a key deliverable was missing from the scope of work. After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path.
What should the project manager do to avoid future delays?

  • A. Submit a change request.
  • B. Add additional resources to the project
  • C. Update the scope of work
  • D. Review the risk management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Baha_Asad
Highly Voted 1 year, 8 months ago
Selected Answer: A
Its A because they studied the impact and they need to submit a change request ( in the execution phase )
upvoted 8 times
...
d482858
Most Recent 2 weeks, 1 day ago
As long as it’s a traditional approach, you can’t make any changes to the scope without a change request.
upvoted 1 times
...
odylec
4 months, 2 weeks ago
Selected Answer: D
You can change the scope now in execution phase and you don't kame a change request to avoid in the future. Look your register
upvoted 2 times
...
GabMonterey
4 months, 3 weeks ago
Selected Answer: A
Updating the scope of work cannot avoid the future delay, change request does.
upvoted 1 times
...
examkitten
5 months, 2 weeks ago
Selected Answer: D
Looks like D. as per similar questions before.
upvoted 3 times
...
Only12go
6 months, 2 weeks ago
Selected Answer: A
In this situation, the project manager should submit a change request (option A). The missing deliverable that impacts the critical path represents a change to the project's scope. By submitting a change request, the project manager can initiate the formal process of documenting, reviewing, and approving scope changes. This helps ensure that the impact of the missing deliverable is properly assessed, and necessary adjustments are made to the project plan to avoid future delays.
upvoted 1 times
...
victory108
8 months ago
Selected Answer: A
A. Submit a change request
upvoted 1 times
...
kevzzz
8 months, 3 weeks ago
Selected Answer: A
You should submit change request forms any time they want to make changes that are likely to affect the scope, budget, or schedule of a project. Team members should fill out change request forms if they need additional resources or want to propose a change to the project plan.
upvoted 1 times
...
Akhundzada
8 months, 3 weeks ago
Selected Answer: C
For example you create a social network website . And you forget login page . After some deliverable completed you see key deliverable missed. I think Update the scope of work is good choice. no need go to CCB. it is key deliverable and you forgot or missed.
upvoted 3 times
adingmaki
6 months, 2 weeks ago
BUT YOU ARE IN THE EXECUTION PART ALREADY! ALL HAS BEEN PLANNED AND BUDGETED BY PROJECT SPONSOR. SYSTEMS THINKING MAN. THINKING SYSTEMS. WE KNOW THAT IT'S EASTY TO WRITE AND ADD. BUT OTHER FACTORS ARE AFFECTED SUCH AS COST, RESOURCES, SCHEDULE CAUSE OF THIS CHANGE.
upvoted 2 times
...
...
Aish_
8 months, 3 weeks ago
Selected Answer: A
Adding a new scope element, even if it's a missing deliverable, can indeed have ripple effects on various aspects of the project. Analyzing the impact of scope changes is crucial to ensure that the changes are feasible, and their consequences are understood. In situations where a missing deliverable impacts the critical path and potential scope changes could have cascading effects, submitting a change request (Option A) is a more comprehensive and structured approach.
upvoted 1 times
...
PaulPMP
1 year, 1 month ago
How can a project manager update the scope without a change request????! The scope is defined beginning of a project stage .and what is the risk management plan ?!! the potential risk affecting the project ! Is scope change a risk ?!!!! not its not. Only aswer "A" is the right choice
upvoted 1 times
...
Weslineo
1 year, 2 months ago
Is it a change request that would authorize change of scope.
upvoted 1 times
...
jartavia05
1 year, 2 months ago
Selected Answer: C
Option C. The key here is: “ do to avoid future delays” update the project scope. Change request is to handle the situation now.
upvoted 2 times
...
modsjunk
1 year, 4 months ago
Selected Answer: D
it says what should he do to avoid that is to manage risk if the qn was what should he do next, then ill choose A to extend the dateline due to change in cp
upvoted 1 times
aqz_111
10 months, 1 week ago
No, based on your explanation, we should update lesson learned register which is not on the list
upvoted 1 times
...
...
PMPStudent
1 year, 4 months ago
Selected Answer: A
"A" makes more sense to me. The second best option is the risk management plan. Risk management plan helps you identify and manage identified and unidentified risks. This situation is an unidentified risk, the risk management plan will help you with how to manage unidentified risks. But since this is a key deliverable and we already know the impact on the critical path, the best path is to just submit the change request as soon as possible and then discuss it with the CCB.
upvoted 2 times
...
KA90
1 year, 5 months ago
Selected Answer: C
C seems correct, as in the context of the question change request is probably referring to adding the missing deliverable, but it does not guarantee avoidance in future delays, revising the scope will.
upvoted 2 times
...
Franco11
1 year, 6 months ago
Selected Answer: A
To Avoid this in the future, a change request should have been initiated to update the scope of work.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...