After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
guyver0523
Highly Voted 2 years, 7 months agorajeshtk
2 years, 7 months ago[Removed]
2 years, 7 months agoPaulPMP
2 years, 1 month agoSuldan
Most Recent 1 week, 2 days agoKim222
8 months agohoomz
1 year, 2 months agojosephsafiran
1 year, 3 months agoOnly12go
1 year, 6 months agoDavid983
1 year, 6 months agoAish_
1 year, 8 months agoThirukj
1 year, 10 months agorajeshtk
2 years agoAlphasham
2 years, 6 months agovictory108
2 years, 6 months agoAdala
2 years, 7 months ago