After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
guyver0523
Highly Voted 2 years, 11 months agorajeshtk
2 years, 10 months ago[Removed]
2 years, 10 months agoPaulPMP
2 years, 4 months agoOnly12go
Highly Voted 1 year, 9 months agoSuldan
Most Recent 3 months, 1 week agoKim222
11 months agohoomz
1 year, 5 months agojosephsafiran
1 year, 6 months agoDavid983
1 year, 9 months agoAish_
1 year, 11 months agoThirukj
2 years, 1 month agorajeshtk
2 years, 3 months agoAlphasham
2 years, 9 months agovictory108
2 years, 9 months agoAdala
2 years, 10 months ago