A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.
What should the project manager do?
Franco11
Highly Voted 2 years, 7 months agoFuwad
1 year, 7 months agohana_truong
11 months agoMaiB
7 months, 1 week agoPeterTheTree
Highly Voted 1 year, 8 months agoSuldan
5 days, 10 hours agoPrincessviv96
Most Recent 1 month agoductrinh
1 month, 1 week agomajidzamani
2 months, 2 weeks agomajidzamani
2 months, 2 weeks agomajidzamani
2 months, 2 weeks agoMeekMan
3 months, 3 weeks agoLifestrongK
5 months agoPragati06
7 months, 2 weeks agoPM_571
7 months, 3 weeks agoSamPMP
9 months, 2 weeks ago723b698
10 months, 3 weeks agoKayon
11 months, 2 weeks agoompk
11 months, 3 weeks agomdkhassan
1 year, 1 month agodjgdgaf
1 year, 2 months ago