A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 9 months agoAcumen88
2 years agosdbol
Most Recent 2 weeks agoArthsath
3 weeks, 3 days agoMTK17
1 month agoSaadalfehri
2 months agobetterthanyesterday
2 months agoHubertP
2 months agoJAQM
2 months, 1 week agoPrincessviv96
2 months, 1 week ago19d3b19
3 months, 1 week agovanwanpmp
4 months agoengamin
4 months, 1 week agoTerryV01
4 months, 1 week agoSMUNENE
5 months agoEZbaba101
5 months, 2 weeks agoFauziYusmin
5 months, 2 weeks agottkong168
6 months, 1 week ago