A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Hao2
Highly Voted 7 months, 2 weeks agoAcumen88
1 year, 11 months agoSaadalfehri
Most Recent 2 weeks, 1 day agobetterthanyesterday
2 weeks, 2 days agoHubertP
2 weeks, 3 days agoJAQM
3 weeks, 1 day agoPrincessviv96
3 weeks, 3 days ago19d3b19
1 month, 2 weeks agovanwanpmp
2 months, 2 weeks agoengamin
2 months, 3 weeks agoTerryV01
2 months, 3 weeks agoSMUNENE
3 months, 1 week agoEZbaba101
3 months, 4 weeks agoFauziYusmin
4 months agottkong168
4 months, 3 weeks agoMalikSaab
5 months agoMrKee
5 months agomahafido
5 months ago