During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?

  • A. Review the project management plan tasks with the stakeholders.
  • B. Review the business benefits realization plan with the stakeholders.
  • C. Review the project management plan budget with the stakeholders.
  • D. Review the communications management plan with the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ndux
2 weeks, 6 days ago
Selected Answer: B
Correct Ans is B
upvoted 1 times
...
ssokratess
3 weeks, 3 days ago
Selected Answer: B
Correct answer is b
upvoted 1 times
...
ssokratess
3 weeks, 3 days ago
Selected Answer: B
Only bb
upvoted 1 times
...
Nayla87
3 months, 2 weeks ago
Selected Answer: B
The question is Related to benefit realization
upvoted 2 times
...
ApaMokus
4 months, 2 weeks ago
Selected Answer: B
Benefit realization is in fact part of the PMP exam. It is covered in Domain III Task 2 of the ECO. (Evaluate and deliver project benefits and value)
upvoted 2 times
...
Princessviv96
4 months, 3 weeks ago
Selected Answer: B
The answer is B
upvoted 1 times
...
Deepakuc
9 months, 1 week ago
Option B
upvoted 1 times
...
053e3de
1 year, 2 months ago
I chose B because the question was talking about business value. Another word for "benefits" that can come out of the project.
upvoted 2 times
...
BuviD
1 year, 7 months ago
Selected Answer: A
A. Review the project management plan tasks with the stakeholders.
upvoted 1 times
...
Kalhan06
1 year, 8 months ago
Selected Answer: B
B is correct.
upvoted 1 times
...
Tuanit
1 year, 10 months ago
Selected Answer: B
B is correct. Projects may perfectly follow schedule, fulfill requirement and meet quality but still can't achieve desired benefit.
upvoted 3 times
...
Lucky_Cindy
1 year, 11 months ago
B is correct
upvoted 1 times
...
Remmy12
1 year, 11 months ago
B. Review the plan with the Stakeholders.
upvoted 1 times
...
Desmonddoyin
2 years, 1 month ago
Selected Answer: B
Reviewing the business benefit plan can help to determine if the project objectives has been met
upvoted 1 times
...
victory108
2 years, 3 months ago
Selected Answer: B
B. Review the business benefits realization plan with the stakeholders
upvoted 1 times
...
BenPappoe
2 years, 3 months ago
Selected Answer: B
Voted B
upvoted 1 times
...
Rena1352
2 years, 3 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...