A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
[Removed]
Highly Voted 2 years, 10 months agorajeshtk
2 years, 10 months agoarnibert
2 years, 9 months agoPMPStudent69
2 years, 6 months agolilylam08
2 years, 4 months agoNayla87
Most Recent 2 months, 4 weeks agoPrincessviv96
3 months, 3 weeks agoPrincessviv96
4 months agoductrinh
4 months, 1 week agoK91
7 months agoLifestrongK
8 months agocrypto_dreams_medellin
8 months, 3 weeks agoCaesar88
1 year, 3 months agoBuviD
1 year, 7 months agoGabMonterey
1 year, 8 months agoAish_
2 years agoMuntadher
2 years agovictory108
2 years, 2 months agoBenPappoe
2 years, 3 months agoAnna12675
2 years, 3 months agowzjh2008
2 years, 4 months agoLeylae
2 years, 4 months agoBakM
1 year, 10 months ago