A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
[Removed]
Highly Voted 2 years, 7 months agorajeshtk
2 years, 7 months agoarnibert
2 years, 6 months agoPMPStudent69
2 years, 3 months agolilylam08
2 years, 1 month agoPrincessviv96
Most Recent 4 weeks agoPrincessviv96
1 month agoductrinh
1 month, 2 weeks agoK91
4 months, 1 week agoLifestrongK
5 months agocrypto_dreams_medellin
5 months, 4 weeks agoCaesar88
1 year agoBuviD
1 year, 4 months agoGabMonterey
1 year, 5 months agoAish_
1 year, 9 months agoMuntadher
1 year, 9 months agovictory108
1 year, 12 months agoBenPappoe
2 years agoAnna12675
2 years agowzjh2008
2 years, 2 months agoLeylae
2 years, 1 month agoBakM
1 year, 7 months agoGanzee
2 years, 4 months ago