exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 287 discussion

Actual exam question from PMI's PMP
Question #: 287
Topic #: 1
[All PMP Questions]

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members.
How should the project manager organize the WBS?

  • A. Customer oriented
  • B. Team oriented
  • C. Cost oriented
  • D. Deliverable oriented
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 2 years, 7 months ago
Selected Answer: D
D is correct
upvoted 8 times
...
rajeshtk
Highly Voted 2 years, 7 months ago
D is the correct answer
upvoted 6 times
...
krispara
Most Recent 4 months ago
Selected Answer: D
WBS focuses on "Deliverables"
upvoted 1 times
...
funmis4
8 months ago
Selected Answer: A
Customer requirements and expectations form the scope baseline ( scope statement +WBS+ WBS Dictionary- Detailed description of each WBS element) WBS is delivered oriented but does not form the bases of scope management by the PM
upvoted 1 times
...
shawndude
1 year, 3 months ago
Selected Answer: D
Create WBS is a process of breaking down the deliverables into smaller and manageable components. It should be a WBS-oriented process.
upvoted 1 times
...
josephsafiran
1 year, 3 months ago
Selected Answer: D
The project manager should organize the Work Breakdown Structure (WBS) as D. Deliverable oriented. A deliverable-oriented WBS organizes and defines the total scope of the project, and represents the work specified in the currently approved project scope statement. Each descending level in the WBS represents an increasingly detailed definition of the project work. This approach helps ensure that no deliverables are missed and that all work performed is aligned with the project’s objectives. However, the project manager should also consider the specific circumstances and dynamics of the project and the team when deciding on the best way to organize the WBS
upvoted 3 times
...
Bruce_Liu
1 year, 3 months ago
Selected Answer: D
D is essential, without D, A would not work.
upvoted 1 times
...
estimater
1 year, 6 months ago
Selected Answer: D
option D
upvoted 1 times
...
Satyabrata_Paul
1 year, 6 months ago
Selected Answer: D
pmi say it is deliverable orientedPMI. https://www.pmi.org/learning/library/applying-work-breakdown-structure-project-lifecycle-6979 A WBS, as defined in the PMBOK® Guide—Third Edition is “a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work. The WBS is decomposed into work packages. The deliverable orientation of the hierarchy includes both internal and external deliverables.”
upvoted 3 times
...
Lucky_Cindy
1 year, 6 months ago
Selected Answer: A
Customer is the first
upvoted 1 times
...
Only12go
1 year, 6 months ago
Selected Answer: D
D. Deliverable oriented The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. The primary purpose of a WBS is to organize and define the total scope of the project in terms of deliverables, so it is deliverable-oriented.
upvoted 3 times
...
Parithi
1 year, 8 months ago
D deliverable oriented
upvoted 1 times
...
Aish_
1 year, 8 months ago
Selected Answer: D
While other orientations (customer-oriented, team-oriented, cost-oriented) can have their merits, a deliverable-oriented WBS is a common and effective approach for breaking down the project's work into manageable components that directly align with the project's goals and final outcomes.
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: D
D. Deliverable oriented
upvoted 1 times
...
sassy2023
1 year, 10 months ago
Selected Answer: D
The Project Management Institute (PMI) Project Management Book of Knowledge (PMBOK) defines the Work Breakdown Structure as a “deliverable oriented hierarchical decomposition of the work to be executed by the project team.” https://www.workbreakdownstructure.com/#:~:text=The%20Project%20Management%20Institute%20(PMI,executed%20by%20the%20project%20team.”
upvoted 2 times
...
ElshRote
1 year, 10 months ago
I selected D. After checking, both forbes.com and wikipedia say a WBS is deliverable-oriented. Forbes.com quoted PMBOK 3rd edition.
upvoted 1 times
...
pmpson
1 year, 11 months ago
I think customer orientation is right. Even if the deliverable is complete, the quality the customer wants is more important.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago