A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the deployment. What should the project manager have done to prevent the delay?
A.
Obtained all critical information ahead of time
B.
Involved the customer in the deployment process
yes, talking with people and explaining a situation and exchanging expectations creates a feeling of appreciation and mutual trust which helps to avoid these situations in most of the cases!
This is the response I got from Chat GPT - While involving the customer in the deployment process (option B) and involving upper management (option D) are also important, they are more reactive measures. Using sample data (option C) might be a temporary workaround but doesn't address the root cause of the delay. Obtaining all critical information ahead of time (option A) is a proactive and strategic approach that effectively prevents such delays.
The best option would be A: Obtained all critical information ahead of time.
By proactively gathering the necessary information before the deployment process begins, the project manager ensures that the team can proceed without delays caused by the customer's postponement. This approach reflects strong planning and risk mitigation, which are crucial for successful project management.
Its important that the project manager should collect all the important and vital information from the client early before starting the project during the requirement gathering phase, this will reduce instances of having to be stuck when the client does not respond on time thereby halting the project progress.
The question says "The customer keeps postposing sending the information which is delaying deployment", I don't think option B is correct because if the customer keeps postposing sending an information, how will the PM get that customer in the deployment process
A: also, it is mentioned the project is close to deployment, so that means the customer was involved in other points of the project, just not the last one. So PM must work on it.
The team is trying to involve the customer but the customer is not collaborating, so the PM must meet with the customer when he or she has time to obtain the info ahead of deployment. We have an issue of communication, so the PM must tailor communications to fit the stakeholder.
A: is the right answer. As a developer, usually you do not involve the customer in deployment process. As they do not understand the technical work. So given the scenario, A would be a preferred choice
According to PMI best practices, the most appropriate action to prevent the delay would be:
A. Obtained all critical information ahead of time
This option aligns with proactive project management principles. By obtaining all critical information in advance, the project manager can mitigate the risk of delays caused by waiting for customer inputs. This ensures that the project has the necessary data to proceed without interruptions, reflecting good planning and risk management.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Erpy
Highly Voted 2 years, 7 months agoarnibert
2 years, 6 months agoShivYad
Highly Voted 10 months, 4 weeks agod2dc878
Most Recent 4 weeks, 1 day agoPrincessviv96
1 month agoductrinh
1 month, 2 weeks agomaya1
1 month, 2 weeks agoshpunk
3 months agowisegik
3 months, 3 weeks agoK91
4 months, 1 week agokavikris
5 months, 1 week agocrypto_dreams_medellin
5 months, 4 weeks agocrypto_dreams_medellin
5 months, 4 weeks agoPhongDang_PM
6 months ago098575305
10 months, 1 week agoAustinIgnatius
11 months agoyassinehelp
11 months ago52d1fe0
1 year ago