exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 409 discussion

Actual exam question from PMI's PMP
Question #: 409
Topic #: 1
[All PMP Questions]

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.
How should the project manager respond?

  • A. Offer guidance and follow up with some developmental activity for the junior team member.
  • B. Refer the junior team member to the senior team member who develops the risk mitigation strategy.
  • C. Inform the junior team member that risk mitigation is not part of their work.
  • D. Tell the junior team member that the information is available in lessons learned.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rajeshtk
Highly Voted 2 years, 1 month ago
A is the correct answer
upvoted 8 times
...
YSO34
Highly Voted 2 years, 2 months ago
Selected Answer: A
Right answer A !
upvoted 7 times
...
segatarasov
Most Recent 8 months, 1 week ago
A is more appropriate here, in my opinion
upvoted 1 times
...
Bruce_Liu
9 months, 2 weeks ago
Selected Answer: A
A is positive and empowering team. Others are not.
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: A
A is correct
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: A
A. Offer guidance and follow up with some developmental activity for the junior team member. In this situation, the project manager should provide guidance and advice to the junior team member on risk mitigation. It's an opportunity for mentorship and knowledge sharing. Additionally, following up with some developmental activities can help the junior team member learn and grow in their role. It's important to support the professional development of team members, especially those who may be less experienced.
upvoted 1 times
...
miggykurkova
1 year, 2 months ago
B is correct. Senior managers are responsible for risk mitigation strategy
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: A
A. Offer guidance and follow up with some developmental activity for the junior team member
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: A
The project manager should respond by offering guidance and advice to the junior team member on risk mitigation. This not only helps the junior team member address their concerns effectively but also provides an opportunity for their professional development. Following up with some developmental activities, such as training or coaching, can further enhance the junior team member's skills and understanding in risk management. This approach promotes a supportive and collaborative environment within the team.
upvoted 1 times
...
kevzzz
1 year, 2 months ago
Selected Answer: B
A team member who does risk mitigation strategy is an SME. The SME in risk management as the mentor to help in risk identification, analysis, risk response planning including when to use a contingency plan, and risk monitoring and control. Any part of mentoring is be done by an SME.
upvoted 4 times
...
sanjiiv
1 year, 7 months ago
Selected Answer: A
Can't be B since No where in the question it's mentioned the senior team member is the one who develop the risk mitigation strategy.
upvoted 1 times
...
[Removed]
1 year, 7 months ago
B - By referring the junior to the senior (expert) who developed the risk mitigation strategy is correct. Shows team collaboration and knowledge is transferred accurately (preferred approach to avoid noise and misunderstanding).
upvoted 1 times
...
Cert_IT
1 year, 10 months ago
Selected Answer: A
I would opt for A
upvoted 2 times
...
PMPStudent
1 year, 10 months ago
Selected Answer: A
A sounds better
upvoted 3 times
...
Bobbie30
1 year, 11 months ago
The answer is most definitely A
upvoted 3 times
...
Alphasham
2 years ago
Selected Answer: A
A is correct.
upvoted 4 times
aqz_111
1 year, 4 months ago
The junior is asking for direction so answer A is servant leader
upvoted 1 times
...
...
[Removed]
2 years, 1 month ago
Selected Answer: A
This is absolutely A. A single team member wouldn't develop risk strategies, that will likely either be up to an entire team or at minimum, the PM.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago