exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 530 discussion

Actual exam question from PMI's PMP
Question #: 530
Topic #: 1
[All PMP Questions]

A project manager has received an updated earned value analysis report. The following are the key findings from the report:
* Budget at completion = US$1 million
* Earned value = US$0,7 million
* Actual cost = US$0,75 million
* Cost performance index = 0,933
Based on this information, what should the project manager conclude about project performance?

  • A. The project will be completed exactly as planned
  • B. The project will be easier to complete than planned
  • C. The project will be difficult to complete as planned
  • D. The project will not be completed as planned
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Delab202
9 months, 1 week ago
Selected Answer: C
A CPI less than 1 indicates that the project is over budget. Specifically, for every dollar spent, the project is only earning 93.3 cents of value. This situation suggests that the project is not as cost-efficient as planned. Given these considerations, the correct conclusion about the project's performance is: C. The project will be difficult to complete as planned. This conclusion is based on the CPI being less than 1, indicating that the project is over budget and thus will require more funds than initially planned or will need to cut costs to meet the original budget, both of which can make the project more challenging to complete as originally planned.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. The project will be difficult to complete as planned
upvoted 1 times
...
Faozi
1 year, 4 months ago
Selected Answer: C
The key finding of the Cost Performance Index (CPI) being 0.933 indicates that the project is performing below expectations in terms of cost efficiency. The Cost Performance Index (CPI) is calculated by dividing the earned value (EV) by the actual cost (AC). In this case, the CPI is less than 1 (0.933), which suggests that the project is over budget. This means that the project is incurring more costs than what has been earned.
upvoted 2 times
...
RanaEisa
1 year, 4 months ago
Why dont w calculate TCPI ; If we calculate it we will get 0.933 which means that B is the answer... and all solutions has the word to complete in it
upvoted 2 times
aqz_111
1 year, 4 months ago
No, the answer should be C because CPI is less than 1 and TCPI = BAC/CPI which is >1 so it get less chance to complete. The answer is C
upvoted 1 times
...
...
jeepTango123456
1 year, 8 months ago
Selected Answer: C
Do is possible, but C is true
upvoted 2 times
...
PMPStudent
1 year, 10 months ago
Selected Answer: C
C is correct. The CPI is not really that bad, it is just under 1. Which means there is still a chance to meet the budget at completion if the project team can fast track an activity or just perform at their best. It is difficult to meet the budget but not impossible.
upvoted 4 times
...
YSO34
2 years, 1 month ago
Selected Answer: D
D is right
upvoted 2 times
[Removed]
2 years, 1 month ago
I think C is a better answer. Its not over yet, so you can't really give a definite yes or a no at this point. Judging by how the rest of it is performing, the project is almost completed and they aren't on track to finish properly.4
upvoted 5 times
rajeshtk
2 years ago
%complete=EV/budget at completion. that is 70% (0.7/1)*100 So the correct answer is C
upvoted 1 times
...
...
rajeshtk
2 years, 1 month ago
why D is correct?
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago