An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.
What should the project manager do to mitigate this risk?
Adeshola1960
Highly Voted 2 years, 3 months agoQuaTV
Most Recent 7 months, 2 weeks agoParamak
9 months, 2 weeks agomdkhassan
1 year, 1 month agojosephsafiran
1 year, 3 months agoBruce_Liu
1 year, 4 months agoDeeski
1 year, 4 months agoChezQW
1 year, 6 months agoLucky_Cindy
1 year, 6 months agoLucky_Cindy
1 year, 6 months agoOnly12go
1 year, 6 months agobu02951
1 year, 6 months agoTuanit
1 year, 6 months agozayn_1983
1 year, 8 months agoFyrus
1 year, 7 months agovictory108
1 year, 8 months agoMuntadher
1 year, 9 months agoAbbasTaki
1 year, 11 months ago