A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 2 years, 4 months agoPrimacomSHU
1 year, 6 months agochxzqw
Highly Voted 2 years, 4 months agocloudreddy
Most Recent 3 weeks, 6 days agokavikris
5 months agoLotToLearn
7 months, 1 week agodiegovcz
9 months agodiegovcz
9 months agoParamak
9 months, 3 weeks agotonybuivannghia
9 months, 3 weeks agonqbaotd
11 months agoakashushi007
11 months, 3 weeks agojiljap
1 year agoMartinussantika
1 year agoMartinussantika
3 months, 1 week agoAwaisalam
1 year, 1 month agosegatarasov
1 year, 2 months agoodylec
1 year, 3 months agoodylec
1 year, 3 months agoleo9944
1 year, 4 months ago