A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
pmp_237student
Highly Voted 2 years, 6 months agoPrimacomSHU
1 year, 7 months agochxzqw
Highly Voted 2 years, 6 months agocloudreddy
Most Recent 2 months, 2 weeks agokavikris
6 months, 3 weeks agoLotToLearn
9 months agodiegovcz
10 months, 3 weeks agodiegovcz
10 months, 3 weeks agoParamak
11 months, 1 week agotonybuivannghia
11 months, 1 week agonqbaotd
1 year agoakashushi007
1 year, 1 month agojiljap
1 year, 2 months agoMartinussantika
1 year, 2 months agoMartinussantika
5 months agoAwaisalam
1 year, 2 months agosegatarasov
1 year, 4 months agoodylec
1 year, 5 months agoodylec
1 year, 5 months agoleo9944
1 year, 5 months ago