An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released. What should the agile team do?
A.
Demand frequent product reviews by the product owner
B.
Continuously work with the product owner to do backlog refinement and product reviews
C.
Have the product owner provide detailed requirement specifications to ensure the proper features are delivered
D.
During the planning session, ensure the team is committed to deliver within the specifications
A. Frequent product reviews alone: While valuable, demanding frequent reviews might strain the product owner's resources and not address continuous refinement.
C. Detailed requirement specifications: This contradicts the agile approach of embracing change. Rigid specifications could lead to wasted effort if features need adjustments based on post-release feedback.
D. Commitment to deliver within specifications: Guaranteeing delivery based on initial specifications during planning can hinder adaptability and responsiveness to future customer needs.
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
chlaithem
10 months, 1 week agoImrangoshi
1 year, 2 months agocurrent_1903
1 year, 7 months agocutri89
1 year, 7 months agoPetrevski
1 year, 7 months agoInvisibleBeing
1 year, 10 months agotianakyi
2 years, 1 month agoKhushboo0612
2 years, 2 months ago