A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
rajeshtk
Highly Voted 2 years, 10 months agodinodragon
1 year, 1 month agoBobbie30
2 years, 7 months agoAish_
Highly Voted 1 year, 11 months agoJamrock
1 year, 11 months agonemm235
1 year, 9 months ago21d5982
Most Recent 2 months agoljz
4 months, 2 weeks ago462729f
5 months agoJordarlu
5 months, 1 week agoWWu
6 months, 2 weeks agoWWu
6 months, 2 weeks ago8d5c185
6 months, 2 weeks agoKim222
10 months, 3 weeks agoea4e1f8
10 months, 3 weeks agotonybuivannghia
12 months agoMusaad
1 year, 6 months agoJaya12
1 year, 7 months agocertificate988
1 year, 7 months agocertificate988
1 year, 7 months agoreaganFF
1 year, 6 months agoOnly12go
1 year, 9 months agoDavid983
1 year, 9 months ago