Exam PMP topic 1 question 539 discussion

Actual exam question from PMI's PMP
Question #: 539
Topic #: 1
[All PMP Questions]

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders.
What should the project manager do?

  • A. Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.
  • B. Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly
  • C. Review the remaining scope and rebaseline the project's schedule to take into account delays in decision making
  • D. Review the adequacy of the project's governance and ensure that an appropriate structure is in place
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: D
Situation is conflicting between senior manager and stakeholder so PM need to review project have well-define project structure
upvoted 2 times
...
Only12go
1 year, 7 months ago
Selected Answer: D
D. Review the adequacy of the project's governance and ensure that an appropriate structure is in place. When a project is being delayed due to contradicting views and decision-making issues involving senior management and external stakeholders, it's essential to review the project's governance structure. The project manager should ensure that the governance structure is appropriate and effectively addresses decision-making processes and conflicts. This may involve revising the governance framework, clarifying roles and responsibilities, and establishing mechanisms for resolving disputes and aligning senior management and external stakeholder interests. A well-defined governance structure can help streamline decision-making and mitigate delays caused by conflicting views.
upvoted 2 times
...
victory108
1 year, 8 months ago
Selected Answer: D
D. Review the adequacy of the project's governance and ensure that an appropriate structure is in place
upvoted 1 times
...
SynikalDemon
1 year, 10 months ago
I like A or C. I going with C.
upvoted 1 times
...
aqz_111
1 year, 11 months ago
Selected Answer: C
As a PM we have to resolve the delay issue right? so answer is C
upvoted 2 times
...
sanjiiv
2 years, 2 months ago
Selected Answer: D
D is correct
upvoted 3 times
...
rajeshtk
2 years, 8 months ago
why not A? Can someone suggest?
upvoted 3 times
[Removed]
2 years, 7 months ago
I think C is correct because its not really a communication problem amongst the stakeholders, its a problem with their views. Therefore the project needs some guidelines on how to govern it, otherwise they'd just argue about everything. This is why usually you see things like boards, steering committees, etc. incorporated in governance procedures, because its rare that everyone views the project in the same way.
upvoted 5 times
Bobbie30
2 years, 5 months ago
Sounds like you're referring to D which is my choice as well
upvoted 1 times
...
Davonos
2 years, 7 months ago
D you mean?
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...