During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?
[Removed]
Highly Voted 2 years, 7 months agoKim222
Most Recent 8 months, 1 week agomrwriting
1 year agoBruce_Liu
1 year, 2 months agoOnly12go
1 year, 6 months agovictory108
1 year, 8 months agoAish_
1 year, 9 months agoJesusisreal
1 year, 9 months agoDawn6699
1 year, 11 months agocwilson91
1 year, 11 months agoHung3102
2 years, 1 month agomeetkamal
2 years, 2 months agoWeslineo
2 years, 2 months agoWeslineo
2 years, 2 months agoPMPStudent
2 years, 4 months agomjs
2 years, 5 months agoFranco11
2 years, 6 months agorajeshtk
2 years, 8 months ago