During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?
[Removed]
Highly Voted 1 year, 7 months agomrwriting
Most Recent 1 week, 5 days agoBruce_Liu
2 months, 1 week agoOnly12go
6 months, 2 weeks agovictory108
8 months, 1 week agoAish_
8 months, 4 weeks agoJesusisreal
9 months, 1 week agoDawn6699
11 months agocwilson91
11 months agoHung3102
1 year, 1 month agomeetkamal
1 year, 2 months agoWeslineo
1 year, 2 months agoWeslineo
1 year, 2 months agoPMPStudent
1 year, 4 months agomjs
1 year, 5 months agoFranco11
1 year, 6 months agorajeshtk
1 year, 7 months ago