During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project.
What should the project manager do?
modsjunk
Highly Voted 2 years agoUppersquareCapital
Highly Voted 11 months, 3 weeks agoba25530
Most Recent 2 weeks, 1 day agoSugansivram
6 months, 1 week agovictory108
1 year, 3 months agoAish_
1 year, 4 months agoJame
1 year, 6 months agoAbbasTaki
1 year, 6 months agosegatarasov
9 months, 2 weeks agonoppy
1 year, 6 months agomangostiffy
1 year, 7 months agoWeslineo
1 year, 10 months agoKA90
2 years, 1 month agorajeshtk
2 years, 3 months ago[Removed]
2 years, 2 months agoBobbie30
2 years agoleo_gold
2 years ago